Pin Pile - Shah Deniz 2, Caspian Sea

14-08-2014

Two Tandem CV-230 Vibro hammer sets (one as back up) were supplied to the Shah Deniz Stage 2 project, one of the largest gas developments in the world. Mobilisation of the set was in September 2014 as shipping routes freeze over during the winter months. The pin pile installation project itself started in February 2015. . 

Reason for equipment choice

  • Avoid risk of pile runs
  • Option to extract if out of tolerance

The video shows the Load test which is done with the CV-230 Tandem.

The CV-230 Tandem set which includes:

  • CV-230 Tandem, clamps, lifting structure, park stand
  • 2 x PU-1180 in Offshore Skid
  • Cable Reel 
  • Hose Reel
  • Master Control Cabin 